View photos of our progress during Week 17. See this previous post for more information on the significant progress made during Week 17. We're getting close to the finish line!
To view photo captions:
Click on the arrow above to begin slideshow. Click on symbol at lower right corner for full screen view. To view photo captions, click on Show Info at top right of screen.
Welcome to the official blog for the Colleyville Public Library Second Floor Expansion Project. Construction began on January 5, 2011 and is scheduled to be completed at the end of April 2011. Please follow our progress via this blog and check back for weekly updates.
Monday, May 23, 2011
Saturday, May 7, 2011
Colleyville Public Library Expansion Project - Week 17
This week a multitude of dramatic visual changes occurred daily on the Colleyville Public Library second floor expansion project, which pushed the project inches from the finish line. The Library was swarming with a sea of workers, who transformed the spaces with an array of finishing touches. On the second floor, millwork installation was completed in the kitchenette, the craft room, the staff work area, the story time room, and in display areas. Painters completed staining millwork, and applied the final coats of paint. Flooring installation of carpet and tile was completed. Doors were hung and glass was installed in millwork windows.
On the first floor, painters completed painting in the new stairwell and teen areas. Workers installed cabinets and bench seating in the teen room and stained millwork. In the new coffee bar space, millwork cabinets were installed and stained. Flooring installation of carpet and tile was completed in the teen and new stairwell areas. Additionally, on the first floor, workers continued to prepare the area for the installation of the new automated check-in system in the drive-thru return area. By the end of this week, the new automated check-in system was installed and operational. Currently, work on the project is on target and will be 98% completed by the end of April 2011. When the construction phase is completed, the shelving installation and moving phases will begin and are scheduled to be completed by the end of May. The official ribbon cutting and grand re-opening celebration in conjunction with the Summer Reading Program kickoff has been scheduled for Monday, June 6, 2011, from 6:30 - 8:30 p.m.
Check back soon for photo slideshow of Week 17. We are in the home stretch!
On the first floor, painters completed painting in the new stairwell and teen areas. Workers installed cabinets and bench seating in the teen room and stained millwork. In the new coffee bar space, millwork cabinets were installed and stained. Flooring installation of carpet and tile was completed in the teen and new stairwell areas. Additionally, on the first floor, workers continued to prepare the area for the installation of the new automated check-in system in the drive-thru return area. By the end of this week, the new automated check-in system was installed and operational. Currently, work on the project is on target and will be 98% completed by the end of April 2011. When the construction phase is completed, the shelving installation and moving phases will begin and are scheduled to be completed by the end of May. The official ribbon cutting and grand re-opening celebration in conjunction with the Summer Reading Program kickoff has been scheduled for Monday, June 6, 2011, from 6:30 - 8:30 p.m.
Check back soon for photo slideshow of Week 17. We are in the home stretch!