Colleyville Public Library Expansion Project - Week 2

The demolition work phase on the Colleyville Public Library second floor expansion project progressed significantly this week. On the second level, carpet, ceiling tile, ceiling grid and lights were removed. On the first floor, demolition work on the meeting room also began, which included removing ceiling tile, ceiling grid and lights. Currently, the main focus of the project is to prepare construction areas for the steel installation phase, which includes the new stairwell and the support I-beam for the second floor meeting room moveable wall. 